Question
|
|
|
NOTE: Only one
answer per question
|
1
|
We split testing into distinct stages primarily
because:
a)
Each test stage has a different purpose.
b)
It is easier to manage testing in stages.
c)
We can run different tests in different environments.
d)
The more stages we have, the better the testing.
|
2
|
Which of the following is likely to benefit most from the use of test
tools providing test capture and replay facilities?
a) Regression testing
b) Integration testing
c) System testing
d)
User acceptance testing
|
3
|
Which of the following statements is NOT
correct?
a)
A minimal test set that achieves 100% LCSAJ coverage will also achieve
100% branch coverage.
b)
A minimal test set that achieves 100% path coverage will also achieve
100% statement coverage.
c)
A minimal test set that achieves 100% path coverage will generally
detect more faults than one that achieves 100% statement coverage.
d)
A minimal test set that achieves 100% statement coverage will generally
detect more faults than one that achieves 100% branch coverage.
|
4
|
Which of the following requirements is testable?
a)
The system shall be user friendly.
b)
The safety-critical parts of the system shall contain 0 faults.
c)
The response time shall be less than one second for the specified
design load.
d)
The system shall be built to be portable.
|
5
|
Analyse the following highly simplified
procedure:
Ask:
“What type of ticket do you require, single or return?”
IF the
customer wants ‘return’
Ask: “What rate, Standard or
Cheap-day?”
IF the customer replies ‘Cheap-day’
Say: “That will be £11:20”
ELSE
Say: “That will be £19:50”
ENDIF
ELSE
Say: “That will be £9:75”
ENDIF
Now decide the minimum number of tests that are
needed to ensure that all
the questions have been asked, all combinations
have occurred and all
replies given.
a)
3
b)
4
c)
5
d)
6
|
6
|
Error guessing:
a)
supplements formal test design techniques.
b)
can only be used in component, integration and system testing.
c)
is only performed in user acceptance testing.
d)
is not repeatable and should not be used.
|
7
|
Which of the following is NOT true of test coverage criteria?
a) Test coverage criteria can be measured in terms of items exercised by a
test suite.
b) A measure of test coverage criteria is the percentage of user
requirements covered.
c) A measure of test coverage criteria is the percentage of faults found.
d)
Test coverage criteria are often
used when specifying test completion criteria.
|
8
|
In prioritising
what to test, the most important objective is to:
a)
find as many faults as possible.
b)
test high risk areas.
c)
obtain good test coverage.
d)
test whatever is easiest to test.
|
9
|
Given the following sets of test management
terms (v-z), and activity descriptions (1-5), which one of the following best
pairs the two sets?
v – test control
w – test
monitoring
x -
test estimation
y - incident management
z - configuration control
1 - calculation of required test resources
2 - maintenance of record of test results
3 - re-allocation of resources when tests
overrun
4 - report on deviation from test plan
5 - tracking of anomalous test results
a)
v-3,w-2,x-1,y-5,z-4
b)
v-2,w-5,x-1,y-4,z-3
c)
v-3,w-4,x-1,y-5,z-2
d)
v-2,w-1,x-4,y-3,z-5
|
10
|
Which one of the following statements about
system testing is NOT true?
a)
System tests are often performed by independent teams.
b)
Functional testing is used more than structural testing.
c)
Faults found during system tests can be very expensive to fix.
d)
End-users should be involved in system tests.
|
11
|
Which of the
following is false?
a)
Incidents should always be fixed.
b)
An incident occurs when expected and actual results
differ.
c)
Incidents can be analysed to assist in test process
improvement.
d)
An incident can be raised against documentation.
|
12
|
Enough testing has been performed when:
a)
time runs out.
b)
the required level of confidence has been achieved.
c)
no more faults are found.
d)
the users won’t find any serious faults.
|
13
|
Which of the following is NOT true of incidents?
a)
Incident resolution is the responsibility of the author of the software
under test.
b)
Incidents may be raised against user requirements.
c)
Incidents require investigation and/or correction.
d)
Incidents are raised when expected and actual results differ.
|
14
|
Which of the
following is not described in a unit test standard?
a)
syntax testing
b)
equivalence partitioning
c)
stress testing
d)
modified condition/decision coverage
|
15
|
Which of the
following is false?
a)
In a system two different failures may have different
severities.
b)
A system is necessarily more reliable after debugging
for the removal of a fault.
c)
A fault need not affect the reliability of a system.
d)
Undetected errors may lead to faults and eventually to
incorrect behaviour.
|
16
|
Which one of the following statements, about
capture-replay tools, is NOT correct?
a)
They are used to support multi-user testing.
b)
They are used to capture and animate user requirements.
c)
They are the most frequently purchased types of CAST tool.
d)
They capture aspects of user behaviour.
|
17
|
How would you
estimate the amount of re-testing likely to be required?
a)
Metrics from previous similar projects
b)
Discussions with the development team
c)
Time allocated for regression testing
d)
a & b
|
18
|
Which of the
following is true of the V-model?
a)
It states that modules are tested against user
requirements.
b)
It only models the testing phase.
c)
It specifies the test techniques to be used.
d)
It includes the verification of designs.
|
19
|
The oracle
assumption:
a)
is that there is some existing system against which
test output may be checked.
b)
is that the tester can routinely identify the correct
outcome of a test.
c)
is that the tester knows everything about the software
under test.
d)
is that the tests are reviewed by experienced testers.
|
20
|
Which of the
following characterises the cost of faults?
a)
They are cheapest to find in the early development
phases and the most expensive to fix in the latest test phases.
b)
They are easiest to find during system testing but the
most expensive to fix then.
c)
Faults are cheapest to find in the early development
phases but the most expensive to fix then.
d)
Although faults are most expensive to find during early
development phases, they are cheapest to fix then.
|
21
|
Which of the
following should NOT normally be an objective for a test?
a)
To find faults in the software.
b)
To assess whether the software is ready for release.
c)
To demonstrate that the software doesn’t work.
d)
To prove that the software is correct.
|
22
|
Which of the following is a form of functional
testing?
a)
Boundary value analysis
b)
Usability testing
c)
Performance testing
d)
Security testing
|
23
|
Which of the
following would NOT normally form part of a test plan?
a)
Features to be tested
b)
Incident reports
c)
Risks
d)
Schedule
|
24
|
Which of these activities provides the biggest potential cost saving
from the use of CAST?
a) Test management
b) Test design
c) Test execution
d)
Test planning
|
25
|
Which of the following is NOT a white box
technique?
a)
Statement testing
b)
Path testing
c)
Data flow testing
d)
State transition testing
|
26
|
Data flow analysis
studies:
a)
possible communications bottlenecks in a program.
b)
the rate of change of data values as a program
executes.
c)
the use of data on paths through the code.
d)
the intrinsic complexity of the code.
|
27
|
In a system
designed to work out the tax to be paid:
An employee has £4000 of salary tax free. The next £1500 is taxed at 10% The next £28000 is taxed at 22% Any further amount is taxed at 40% To the nearest whole pound, which of these is a valid Boundary Value Analysis test case?
a)
£1500
b)
£32001
c)
£33501
d)
£28000
|
28
|
An important
benefit of code inspections is that they:
a)
enable the code to be tested before the execution
environment is ready.
b)
can be performed by the person who wrote the code.
c)
can be performed by inexperienced staff.
d)
are cheap to perform.
|
29
|
Which of the following is the best source of Expected Outcomes for User
Acceptance Test scripts?
a) Actual results
b) Program specification
c)
User requirements
d)
System specification
|
30
|
What is the main
difference between a walkthrough and an inspection?
a)
An inspection is lead by the author, whilst a
walkthrough is lead by a trained moderator.
b)
An inspection has a trained leader, whilst a
walkthrough has no leader.
c)
Authors are not present during inspections, whilst they
are during walkthroughs.
d)
A walkthrough is lead by the author, whilst an
inspection is lead by a trained moderator.
|
31
|
Which one of the
following describes the major benefit of verification early in the life
cycle?
a)
It allows the identification of changes in user
requirements.
b)
It facilitates timely set up of the test environment.
c)
It reduces defect multiplication.
d)
It allows testers to become involved early in the
project.
|
32
|
Integration testing
in the small:
a)
tests the individual components that have been
developed.
b)
tests interactions between modules or subsystems.
c)
only uses components that form part of the live system.
d)
tests interfaces to other systems.
|
33
|
Static analysis is best described as:
a)
the analysis of batch programs.
b)
the reviewing of test plans.
c)
the analysis of program code.
d)
the use of black box testing.
|
34
|
Alpha testing is:
a)
post-release testing by end user representatives at the
developer’s site.
b)
the first testing that is performed.
c)
pre-release testing by end user representatives at the
developer’s site.
d)
pre-release testing by end user representatives at
their sites.
|
35
|
A failure is:
a)
found in the software; the result of an error.
b)
departure from specified behaviour.
c)
an incorrect step, process or data definition in a
computer program.
d)
a human action that produces an incorrect result.
|
36
|
In a system
designed to work out the tax to be paid:
An employee has £4000 of salary tax free. The next £1500 is taxed at 10% The next £28000 is taxed at 22% Any further amount is taxed at 40% Which of these groups of numbers would fall into the same equivalence class?
a)
£4800; £14000; £28000
b)
£5200; £5500; £28000
c)
£28001; £32000; £35000
d)
£5800; £28000; £32000
|
37
|
The most important
thing about early test design is that it:
a)
makes test preparation easier.
b)
means inspections are not required.
c)
can prevent fault multiplication.
d)
will find all faults.
|
38
|
Which of the
following statements about reviews is true?
a)
Reviews cannot be performed on user requirements
specifications.
b)
Reviews are the least effective way of testing code.
c)
Reviews are unlikely to find faults in test plans.
d)
Reviews should be performed on specifications, code,
and test plans.
|
39
|
Test cases are
designed during:
a)
test recording.
b)
test planning.
c)
test configuration.
d)
test specification.
|
40
|
A configuration management system would NOT
normally provide:
a)
linkage of customer requirements to version numbers.
b)
facilities to compare test results with expected results.
c)
the precise differences in versions of software component source code.
d)
restricted access to the source code library.
|
For More Questions and Answers:
Flipkart:
http://www.flipkart.com/advanced-test-strategy-istqb-foundation-questions-answers-included/p/itmdp9yzkgedxghz?pid=9781482812220
Amazon:
http://www.amazon.com/Advanced-Test-Strategy-Foundation--Questions-ebook/dp/B00FKS462K/
No comments:
Post a Comment